The Biomedical & Health Sciences Building will include research and teaching labs, classrooms, and administrative and faculty offices for health sciences. The first phase in a multi-phase research complex, the facility will house the medical education program, as well as the WSU College of Pharmacy.

Projected construction timeline

  • Aug. 2011 - Soil Remediation Start
  • Oct. 2011 - Soil Remediation Complete
  • Oct. 2011 - Building Construction Start
  • Aug. 2013 - Building Construction Complete
  • Fall 2013 - Commissioning/Move-in
  • Jan 2014 - Occupancy

About the building

  • Size: 125,000 gross square feet
  • Total Project Cost: $78.6 million. The state legislature allocated $35 million toward the construction cost in 2011 and approved an additional $37 million in 2012.
  • Architect: NBBJ, Seattle, WA
  • General Contractor/Construction Manager: Graham Construction & Management